Street Construction Updates | The City of Lakewood, Ohio

Street Construction Updates


2020 Street Construction Updates as of 8/22/20

2020 Watermains

IDLEWOOD – The street has been fully paved and most site restoration has been completed.  Seeding will take place later this Fall. Also, United Survey will perform planned sewer lining work next.

MORRISON – New concrete has been placed over the new waterline trenches. Most of the replacement curb and apron work has been completed.  The rest of the street has been milled and covered with intermediate asphalt.  Surface asphalt is planned for next week.  Sewer rehabilitation is ongoing.

LAKELAND – New watermain installed and all house service line connections completed.  Trench over new waterline has been cut and excavated down to planned subgrade (removed concrete), prepping for concrete pour early next week.  After which the remaining portion of the street will be milled, intermediate asphalt placed, and full-depth repairs will take place.  Sewer rehabilitation is on-going.

2020 Resurfacing

Athens (Bunts – Brown) ; All curbs/aprons/sidewalk replacement work completed, including restoration (except seeding).  Final surface course of asphalt planned for late September.  New colored/stamped crosswalks will be installed at Richland (N & S sides of the intersection) after the final surface course of asphalt.

Bayes (Brown – Warren): New curbs/aprons/sidewalk replacement work completed this week.  Final surface course of asphalt planned for late September.

Delaware (Alger – Arthur): Curb/apron/sidewalk replacement work started on 8/21/20.  Final surface course of asphalt planned for late September.  New colored/stamped crosswalks will be installed at Arthur (N & S sides of the intersection) and at Mars Ave (N. side of intersection) after the final surface course of asphalt..

McKinley (Riverside – S. Marginal):  No work performed this week on McKinley. Curbs/aprons/sidewalk have been marked out for replacement.  Concrete work will not start for a week or two.

Daleview (McKinley – Riverside):  Completed full-depth base repairs this week.  Curbs/aprons/sidewalk have been marked out for replacement.  Concrete work will not start for a couple weeks.

Wagar (Detroit – Madison): Full-depth base repairs completed this week. Curbs/aprons/sidewalk have not been marked out for replacement yet.  Concrete work will not start for a couple weeks.

Forest Cliff:  Full-depth base repairs are planned for early next week.  Curbs/aprons/sidewalk have not been marked out for replacement yet.  Concrete work will not start for a couple weeks.

Parkside: Full-depth base repairs are planned for early next week.  Curbs/aprons/sidewalk have not been marked out for replacement yet.  Concrete work will not start for a couple weeks.

Ridgewood: Curbs/aprons/sidewalk have not yet been marked out for replacement yet.  Concrete work will not start for a couple weeks.

Lake Ave:   Striping has been completed.  “No Parking – Bike Lane” signs will  be ready for posting in  2-3 weeks.